Project Summary

The Work includes demolition of the existing water treatment plant and iron filter. Construction of a new 2000 sf masonry and framed water treatment plant, including all new site utilities. Furnish and install new Deep Well Turbine Pump, Horizontal Pressure Filter System, Emergency Gas Scrubber System, Fluoridation and Chlorination Equipment. Integration of SCADA controls and Start up services. The site receives new asphalt drive and general landscape restoration.